Overview: JALAN PADANG 1, JALAN PADANG 2 AND JALAN PADANG 3, KAMPUNG MELAYU MAJIDI - UPGRADING WORKS OF ROAD AND DRAINAGE SYSTEM is a Roadworks, Drainage System construction project in Johor. The scope is recorded as Renovation & Upgrading. JALAN PADANG 1, JALAN PADANG 2 AND JALAN is currently recorded at Mobilization. The main contractor has been awarded. Construction started Mar 2018, with target completion Jul 2018. The project value is recorded in the Less than 1 million range. myBina has identified 3 companies across 3 roles on JALAN PADANG 1, JALAN PADANG 2 AND JALAN: 1 developer, 1 consultant and 1 contractor. This record was last verified on 20 February 2018 (Issue 201802.3).
| Project ID | : | 62113 |
| Issue Number | : | 201802.3 |
| Project Status | : | Mobilization |
| Job Award Status | : | Main contractor awarded |
| State | : | Johor |
| Category | : | Roadworks, Drainage System |
| Full Address | : | |
| Construction Start | : | Mar 2018 |
| Target Completion | : | Jul 2018 |
| Project Ownership | : | Private |
| Project Works | : | Renovation & Upgrading |
| Value Range | : | Less than 1 million |
| Project Value | : | |
| Contractor Spec | : | |
| Tender Deadline | : |
Full project details are on record for JALAN PADANG 1, JALAN PADANG 2 AND JALAN PADANG 3, KAMPUNG MELAYU MAJIDI - UPGRADING WORKS OF ROAD AND DRAINAGE SYSTEM, covering the scope of works, site arrangement and contract structure. Available to myBina subscribers.
Recorded specifications for this project cover structural, M&E and finishes requirements, alongside contractor grade and tender details. Available to myBina subscribers.
myBina has identified 3 companies across 3 roles on JALAN PADANG 1, JALAN PADANG 2 AND JALAN PADANG 3, KAMPUNG MELAYU MAJIDI - UPGRADING WORKS OF ROAD AND DRAINAGE SYSTEM: 1 developer, 1 consultant and 1 contractor.
Contact us to reveal company names, phone numbers, emails and full contact details.
Other Roadworks, Drainage System construction projects recorded by myBina in Johor:
- RUMAH LORONG AMAN, KAMPUNG MELAYU, JOHOR BAHRU - SHEET PILING WORKS
- NEIGHBOURHOOD 9 @ BANDAR DATO ONN - INFRASTRUCTURE WORKS (PHASE 2)
- JALAN KENYALANG AND JALAN LANGKASUKA, LARKIN - UPGRADING OF INFRASTRUCTURE WORKS
- MAJLIS BANDARAYA JOHOR BAHRU @ MIDDLE ZONE - UPGRADING AND MAINTENANCE WORKS OF BUS STOP (2018)
- MAJLIS BANDARAYA JOHOR BAHRU @ WEST ZONE - UPGRADING AND MAINTENANCE WORKS OF BUS STOP (2018)
Need access to all 10,000+ projects?
A myBina membership gives you unlimited access across all states, categories and project statuses — with alerts, CRM tools and export features.
Contact Us