Overview: KOTA BAYUEMAS - PHASE A8A is a Linkhouses construction project in Selangor. KOTA BAYUEMAS is currently recorded at Construction - Piling & Foundation Works, with substructure works underway on site. Construction started Mar 2010, with target completion Dec 2011. The project value is recorded in the Between 10 and 50 million range. myBina has identified 6 companies across 6 roles on KOTA BAYUEMAS: 1 developer, 1 civil / structural engineer, 1 mech. / electrical engineer, 1 quantity surveyor and 2 other roles. This record was last verified on 15 April 2010 (Issue 201007.1).
| Project ID | : | 18819 |
| Issue Number | : | 201007.1 |
| Project Status | : | Construction - Piling & Foundation Works |
| State | : | Selangor |
| Category | : | Linkhouses |
| Full Address | : | |
| Construction Start | : | Mar 2010 |
| Target Completion | : | Dec 2011 |
| Project Ownership | : | Private |
| Value Range | : | Between 10 and 50 million |
| Project Value | : | |
| Contractor Spec | : | |
| Tender Deadline | : |
Full project details are on record for KOTA BAYUEMAS - PHASE A8A, covering the scope of works, site arrangement and contract structure. Available to myBina subscribers.
Recorded specifications for this project cover structural, M&E and finishes requirements, alongside contractor grade and tender details. Available to myBina subscribers.
myBina has identified 6 companies across 6 roles on KOTA BAYUEMAS - PHASE A8A: 1 developer, 1 civil / structural engineer, 1 mech. / electrical engineer, 1 quantity surveyor and 2 other roles.
Contact us to reveal company names, phone numbers, emails and full contact details.
Other Linkhouses construction projects recorded by myBina in Selangor:
Need access to all 10,000+ projects?
A myBina membership gives you unlimited access across all states, categories and project statuses — with alerts, CRM tools and export features.
Contact Us