A total of 980 construction projects entered the myBina database in August 2026. That is 19.1% lower than July 2026, and 52.6% higher against August 2025. The estimated construction value of that intake is RM154.77 billion; 976 of the 980 records carry a value we can total.
980new projects
RM154.77 billionestimated value
−19.1%vs Jul 2026
+52.6%vs Aug 2025
327stage changes
The month in numbers
Value tells a softer story: RM154.77 billion for the month, 38.9% lower than July 2026 and 11.1% higher than August 2025, at an average of RM158.6 million per reported project (24.4% lower).
Aug 2026
Jul 2026
Aug 2025
MoM
YoY
Projects reported
980
1,211
642
−19.1%
+52.6%
Estimated value
RM154.77 billion
RM253.26 billion
RM139.26 billion
−38.9%
+11.1%
Records carrying a value
976
1,208
638
—
Where the work is: sector by sector
Residential accounted for the largest share of August 2026 intake: 207 projects, 21.1% of everything reported, at an estimated RM6.64 billion. Against July 2026 it is 0.5% lower; against August 2025, 41.8% higher. Infrastructure follows with 138 projects (RM29.7 billion, 28.1% lower month-on-month); Industrial follows with 126 projects (RM63.09 billion, 4.5% lower month-on-month). Watch Others: 8 projects, 700.0% higher month-on-month, the widest move in the table.
Sector
Aug 2026
Jul 2026
MoM
Aug 2025
YoY
Est. value
Share
Residential
207
208
−0.5%
146
+41.8%
RM6.64 billion
21.1%
Infrastructure
138
192
−28.1%
79
+74.7%
RM29.7 billion
14.1%
Industrial
126
132
−4.5%
63
+100.0%
RM63.09 billion
12.9%
Education
97
140
−30.7%
44
+120.5%
RM1.77 billion
9.9%
Residential-up Market
88
111
−20.7%
76
+15.8%
RM10.18 billion
9.0%
Commercial
85
102
−16.7%
71
+19.7%
RM10.42 billion
8.7%
Utilities
83
119
−30.3%
54
+53.7%
RM3.05 billion
8.5%
Government Buildings
47
69
−31.9%
28
+67.9%
RM1.46 billion
4.8%
Hotel / Service Apartment
46
53
−13.2%
24
+91.7%
RM13.26 billion
4.7%
Medical
19
37
−48.6%
20
−5.0%
RM2.55 billion
1.9%
Public Amenities
15
29
−48.3%
20
−25.0%
RM100.5 million
1.5%
Mixed Development
14
12
+16.7%
11
+27.3%
RM12.48 billion
1.4%
Others
8
1
+700.0%
2
+300.0%
RM18.9 million
0.8%
Recreation
7
6
+16.7%
3
+133.3%
RM38.1 million
0.7%
Projects on the move
August 2026 carried 327 recorded stage changes across projects already on file, 37.0% lower against July 2026. Leading the movement: 54 moved from Tender / Evaluation to Construction - Site Works; 43 moved from Construction - Piling & Foundation Works to Construction - Structural; 31 moved from Construction - Site Works to Construction - Structural. These counts reflect stage changes captured in a new project revision during the month and are a floor, not a census.
The month's largest reported projects
The 6 highest-value projects entering our database in August 2026.
Values are our reported estimate. Residential records classified as private bungalow or private housing are not listed.
On the map, 211 projects (21.5%) landed in Selangor, an estimated RM16.08 billion, and 20.4% lower than July 2026. Next came Perak (146) and Pulau Pinang (127).
State
Projects
Jul 2026
MoM
Est. value
Selangor
211
265
−20.4%
RM16.08 billion
Perak
146
106
+37.7%
RM35.68 billion
Pulau Pinang
127
168
−24.4%
RM38.54 billion
Johor
86
102
−15.7%
RM27.97 billion
Kedah
73
78
−6.4%
RM2.18 billion
Sabah
67
109
−38.5%
RM6.54 billion
Sarawak
57
120
−52.5%
RM2.99 billion
W.P. Kuala Lumpur
52
71
−26.8%
RM15.13 billion
Pahang
41
32
+28.1%
RM1.49 billion
Kelantan
27
18
+50.0%
RM632.2 million
Negeri Sembilan
26
51
−49.0%
RM4.27 billion
Terengganu
20
32
−37.5%
RM1.08 billion
Melaka
15
34
−55.9%
RM1.36 billion
W.P. Putrajaya
15
8
+87.5%
RM275.2 million
Perlis
11
12
−8.3%
RM190 million
W.P. Labuan
4
1
+300.0%
RM126 million
How big were they
The size mix shows 46 projects above RM500 million, 4.7% of intake and 35.2% lower month-on-month, against 307 below RM10 million.
Tendering and awards
On procurement, the month’s projects break down as Main contractor awarded (701), Subcontractor awarded (245), Subcontractor tender (62). A project may carry more than one award status, so these do not sum to the month total.
What it adds up to
Against August 2025 the month is clearly ahead, even where the month-on-month figure is softer, a reminder that a single month is a noisier series than a year.
Citing this page
Free to quote with attribution to myBina. Suggested form:
myBina August 2026 Malaysian Construction Digest — https://www.mybina.com.my/digest.php?m=2026-08
For the underlying project records, or a figure not shown here, contact us.
How these numbers are built
What a "new project" is. A project counted in August 2026 is one myBina first
reported that month. That is a reporting date, not a groundbreaking date — a job may have been planned or
tendered earlier. This is a measure of what entered the record in the month.
Value is an estimate. Many records state a value band rather than a figure, so the midpoint of the
band is used. 976 of 980 records this month
(99.6%) carry a value we can
total; the rest contribute nothing, so the total is a floor rather than a market size.
One sector per project. Sector shares use each project's main category, so they add to 100%.
Award status is the exception: a project can carry more than one, and that table is counted per status.
Stage changes are recorded, not inferred from site activity. A change is counted when a project's
new revision carries a different stage from its previous one. Changes corrected within an existing revision
are not visible to this count, which makes it a minimum.
Scope. Verified, live project records only. Cancelled records are excluded, and residential records
classified as private bungalow or private housing are excluded from the named projects.
Frozen on publication. These figures were computed on
28 September 2026 and are not recalculated, so a figure cited from this page stays as cited.
The projects behind these numbers
myBina members see every project in this digest by name, with value, stage, specification
and the companies attached to each job.
myBina Construction Digest · August 2026 · mybina.com.my
· figures computed 28 September 2026.
Values are estimates from reported value bands; counts are projects first reported in the month.