JUNE 2026 · Malaysia
myBina recorded 373 new construction projects across Malaysia in June 2026, 5.1% lower than May 2026 and 5.4% higher than June 2025. Together they represent an estimated RM28.28 billion in construction value, based on the 370 records out of 373 where a value is on file.
Value tells a softer story: RM28.28 billion for the month, 24.1% lower than May 2026 and 46.8% higher than June 2025, at an average of RM76.4 million per reported project (21.5% lower).
| Jun 2026 | May 2026 | Jun 2025 | MoM | YoY | |
|---|---|---|---|---|---|
| Projects reported | 373 | 393 | 354 | −5.1% | +5.4% |
| Estimated value | RM28.28 billion | RM37.28 billion | RM19.27 billion | −24.1% | +46.8% |
| Records carrying a value | 370 | 383 | 352 | — | |
Utilities accounted for the largest share of June 2026 intake: 57 projects, 15.3% of everything reported, at an estimated RM5.87 billion. That is 29.5% higher than May 2026 and 18.8% higher than June 2025. Residential follows with 57 projects (RM1.54 billion, 3.6% higher month-on-month); Infrastructure follows with 54 projects (RM1.18 billion, 18.2% lower month-on-month). Public Amenities posted the month’s largest swing, 87.5% higher against May 2026 on 15 projects.
| Sector | Jun 2026 | May 2026 | MoM | Jun 2025 | YoY | Est. value | Share |
|---|---|---|---|---|---|---|---|
| Utilities | 57 | 44 | +29.5% | 48 | +18.8% | RM5.87 billion | 15.3% |
| Residential | 57 | 55 | +3.6% | 59 | −3.4% | RM1.54 billion | 15.3% |
| Infrastructure | 54 | 66 | −18.2% | 54 | 0.0% | RM1.18 billion | 14.5% |
| Education | 51 | 67 | −23.9% | 29 | +75.9% | RM480.7 million | 13.7% |
| Industrial | 36 | 34 | +5.9% | 32 | +12.5% | RM7.75 billion | 9.7% |
| Commercial | 26 | 41 | −36.6% | 44 | −40.9% | RM453.5 million | 7.0% |
| Residential-up Market | 26 | 28 | −7.1% | 39 | −33.3% | RM2.77 billion | 7.0% |
| Government Buildings | 17 | 13 | +30.8% | 20 | −15.0% | RM225.3 million | 4.6% |
| Hotel / Service Apartment | 16 | 17 | −5.9% | 4 | +300.0% | RM4.71 billion | 4.3% |
| Public Amenities | 15 | 8 | +87.5% | 14 | +7.1% | RM80.5 million | 4.0% |
| Medical | 9 | 11 | −18.2% | 4 | +125.0% | RM800.9 million | 2.4% |
| Mixed Development | 4 | 4 | 0.0% | 3 | +33.3% | RM2.41 billion | 1.1% |
| Others | 3 | 3 | 0.0% | 1 | +200.0% | RM12.9 million | 0.8% |
| Recreation | 2 | 2 | 0.0% | 3 | −33.3% | RM3 million | 0.5% |
Existing projects moved stage 296 times in June 2026 as recorded by our editors, 2.0% lower than the month before. Leading the movement: 67 moved from Tender / Evaluation to Construction - Site Works; 52 moved from Construction - Piling & Foundation Works to Construction - Structural; 30 moved from Construction - Site Works to Construction - Structural. The figure counts changes recorded against a new revision within the month, so it should be read as a minimum.
The 6 highest-value projects entering our database in June 2026. Values are our reported estimate. Residential records classified as private bungalow or private housing are not listed.
Geographically, Selangor took 99 of the month’s projects (26.5%), worth an estimated RM9.27 billion, 3.9% lower than May 2026. Perak (47) and Sarawak (39) followed.
| State | Projects | May 2026 | MoM | Est. value |
|---|---|---|---|---|
| Selangor | 99 | 103 | −3.9% | RM9.27 billion |
| Perak | 47 | 48 | −2.1% | RM4.82 billion |
| Sarawak | 39 | 58 | −32.8% | RM1.02 billion |
| Johor | 35 | 38 | −7.9% | RM3.02 billion |
| W.P. Kuala Lumpur | 32 | 20 | +60.0% | RM4.65 billion |
| Pulau Pinang | 28 | 23 | +21.7% | RM1.35 billion |
| Kedah | 20 | 24 | −16.7% | RM928.2 million |
| Pahang | 18 | 18 | 0.0% | RM391.1 million |
| Sabah | 15 | 22 | −31.8% | RM646 million |
| Negeri Sembilan | 10 | 5 | +100.0% | RM279.2 million |
| Kelantan | 10 | 8 | +25.0% | RM427 million |
| W.P. Putrajaya | 8 | 9 | −11.1% | RM1.1 billion |
| Perlis | 4 | 2 | +100.0% | RM80.9 million |
| Melaka | 3 | 11 | −72.7% | RM66 million |
| Terengganu | 2 | 4 | −50.0% | RM20 million |
| Outside Malaysia | 1 | 0 | n/a | RM100 million |
3.2% of June 2026’s projects (12 of them) carry a value above RM500 million, 14.3% lower than May 2026; 162 fall under RM10 million.
On procurement, the month’s projects break down as Main contractor awarded (227), Subcontractor awarded (39), Subcontractor tender (3). A project may carry more than one award status, so these do not sum to the month total.
Against June 2025 the month is clearly ahead, even where the month-on-month figure is softer — a reminder that a single month is a noisier series than a year.
myBina Construction Digest · June 2026 · mybina.com.my · figures computed 20 October 2026. Values are estimates from reported value bands; counts are projects first reported in the month.