May 2026 closed with 393 newly reported construction projects on myBina, running 20.6% higher than the previous month and 9.5% higher than a year earlier. Together they represent an estimated RM37.28 billion in construction value, based on the 383 records out of 393 where a value is on file.
393new projects
RM37.28 billionestimated value
+20.6%vs Apr 2026
+9.5%vs May 2025
302stage changes
The month in numbers
By value, the month climbed 8.4% higher month-on-month to RM37.28 billion, and stands 32.1% lower against May 2025. The average reported project is worth RM97.3 million, 8.0% lower on April 2026.
May 2026
Apr 2026
May 2025
MoM
YoY
Projects reported
393
326
359
+20.6%
+9.5%
Estimated value
RM37.28 billion
RM34.38 billion
RM54.92 billion
+8.4%
−32.1%
Records carrying a value
383
325
355
—
Where the work is: sector by sector
Sector by sector, Education led May 2026 with 67 new projects (17.0% of the month) worth an estimated RM516.1 million. Against April 2026 it is 86.1% higher; against May 2025, 415.4% higher. Infrastructure follows with 66 projects (RM8.93 billion, 7.0% lower month-on-month); Residential follows with 55 projects (RM1.11 billion, 10.0% higher month-on-month). Watch Mixed Development: 4 projects, 300.0% higher month-on-month, the widest move in the table.
Sector
May 2026
Apr 2026
MoM
May 2025
YoY
Est. value
Share
Education
67
36
+86.1%
13
+415.4%
RM516.1 million
17.0%
Infrastructure
66
71
−7.0%
55
+20.0%
RM8.93 billion
16.8%
Residential
55
50
+10.0%
61
−9.8%
RM1.11 billion
14.0%
Utilities
44
45
−2.2%
53
−17.0%
RM8.68 billion
11.2%
Commercial
41
28
+46.4%
23
+78.3%
RM1.25 billion
10.4%
Industrial
34
25
+36.0%
41
−17.1%
RM11.04 billion
8.7%
Residential-up Market
28
20
+40.0%
38
−26.3%
RM1.86 billion
7.1%
Hotel / Service Apartment
17
15
+13.3%
13
+30.8%
RM2.74 billion
4.3%
Government Buildings
13
16
−18.8%
31
−58.1%
RM183 million
3.3%
Medical
11
5
+120.0%
7
+57.1%
RM567.6 million
2.8%
Public Amenities
8
13
−38.5%
11
−27.3%
RM51.1 million
2.0%
Mixed Development
4
1
+300.0%
9
−55.6%
RM340 million
1.0%
Others
3
0
n/a
0
n/a
RM5.3 million
0.8%
Recreation
2
1
+100.0%
4
−50.0%
RM9.4 million
0.5%
Projects on the move
myBina captured 302 recorded status changes on existing projects during May 2026, 15.2% lower than April 2026. The most common moves were: 57 moved from Tender / Evaluation to Construction - Site Works; 48 moved from Construction - Piling & Foundation Works to Construction - Structural; 28 moved from Construction - Site Works to Construction - Piling & Foundation Works. Only stage changes written into a fresh revision in the month are counted here, which makes this a conservative measure.
The month's largest reported projects
The 6 highest-value projects entering our database in May 2026.
Values are our reported estimate. Residential records classified as private bungalow or private housing are not listed.
On the map, 103 projects (26.2%) landed in Selangor, an estimated RM3.16 billion, and 51.5% higher than April 2026. Next came Sarawak (58) and Perak (48).
State
Projects
Apr 2026
MoM
Est. value
Selangor
103
68
+51.5%
RM3.16 billion
Sarawak
58
31
+87.1%
RM5.66 billion
Perak
48
30
+60.0%
RM3.48 billion
Johor
38
29
+31.0%
RM10.96 billion
Kedah
24
27
−11.1%
RM795.6 million
Pulau Pinang
23
38
−39.5%
RM1.09 billion
Sabah
22
24
−8.3%
RM7.27 billion
W.P. Kuala Lumpur
20
20
0.0%
RM1.54 billion
Pahang
18
14
+28.6%
RM1.51 billion
Melaka
11
5
+120.0%
RM146.2 million
W.P. Putrajaya
9
8
+12.5%
RM185.8 million
Kelantan
8
6
+33.3%
RM1.26 billion
Negeri Sembilan
5
11
−54.5%
RM117 million
Terengganu
4
7
−42.9%
RM80 million
Perlis
2
5
−60.0%
RM18 million
How big were they
The size mix shows 14 projects above RM500 million, 3.6% of intake and 22.2% lower month-on-month, against 166 below RM10 million.
Tendering and awards
On procurement, the month’s projects break down as Main contractor awarded (276), Subcontractor awarded (46), Subcontractor tender (9). A project may carry more than one award status, so these do not sum to the month total.
What it adds up to
With month-on-month and year-on-year both positive, May 2026 marks a genuine step up in reported pipeline rather than a single strong week.
Citing this page
Free to quote with attribution to myBina. Suggested form:
myBina May 2026 Malaysian Construction Digest — https://www.mybina.com.my/digest.php?m=2026-05
For the underlying project records, or a figure not shown here, contact us.
How these numbers are built
What a "new project" is. A project counted in May 2026 is one myBina first
reported that month. That is a reporting date, not a groundbreaking date — a job may have been planned or
tendered earlier. This is a measure of what entered the record in the month.
Value is an estimate. Many records state a value band rather than a figure, so the midpoint of the
band is used. 383 of 393 records this month
(97.5%) carry a value we can
total; the rest contribute nothing, so the total is a floor rather than a market size.
One sector per project. Sector shares use each project's main category, so they add to 100%.
Award status is the exception: a project can carry more than one, and that table is counted per status.
Stage changes are recorded, not inferred from site activity. A change is counted when a project's
new revision carries a different stage from its previous one. Changes corrected within an existing revision
are not visible to this count, which makes it a minimum.
Scope. Verified, live project records only. Cancelled records are excluded, and residential records
classified as private bungalow or private housing are excluded from the named projects.
Frozen on publication. These figures were computed on
20 October 2026 and are not recalculated, so a figure cited from this page stays as cited.
The projects behind these numbers
myBina members see every project in this digest by name, with value, stage, specification
and the companies attached to each job.
myBina Construction Digest · May 2026 · mybina.com.my
· figures computed 20 October 2026.
Values are estimates from reported value bands; counts are projects first reported in the month.