Overview: BUKIT TENGAH : BUKIT MERTAJAM - 132KV DOUBLE CIRCUIT TRANSMISSION LINE is a government Transmission line construction project in Pulau Pinang. BUKIT TENGAH : BUKIT MERTAJAM is currently recorded at Construction - Site Works, with external and finishing works in progress. Construction started May 2012, with target completion May 2013. The project value is recorded in the Between 1 and 10 million range. myBina has identified 3 companies across 3 roles on BUKIT TENGAH : BUKIT MERTAJAM: 1 developer, 1 consultant and 1 contractor. This record was last verified on 16 July 2012 (Issue 201210.2).
| Project ID | : | 29339 |
| Issue Number | : | 201210.2 |
| Project Status | : | Construction - Site Works |
| State | : | Pulau Pinang |
| Category | : | Transmission line |
| Full Address | : | |
| Construction Start | : | May 2012 |
| Target Completion | : | May 2013 |
| Project Ownership | : | Government |
| Value Range | : | Between 1 and 10 million |
| Project Value | : | |
| Contractor Spec | : | |
| Tender Deadline | : |
Full project details are on record for BUKIT TENGAH : BUKIT MERTAJAM - 132KV DOUBLE CIRCUIT TRANSMISSION LINE, covering the scope of works, site arrangement and contract structure. Available to myBina subscribers.
Recorded specifications for this project cover structural, M&E and finishes requirements, alongside contractor grade and tender details. Available to myBina subscribers.
myBina has identified 3 companies across 3 roles on BUKIT TENGAH : BUKIT MERTAJAM - 132KV DOUBLE CIRCUIT TRANSMISSION LINE: 1 developer, 1 consultant and 1 contractor.
Company names, phone numbers, emails and full contact details are included in a myBina subscription.
Other Transmission line construction projects recorded by myBina in Pulau Pinang:
- PMU 132KV TASEK GELUGOR SWITCHING STATION
- PMU PERAI GIS AND PMU SEBERANG JAYA TO PPU JALAN TENAGA : MILL AND PAVE WORK
- PPU PERMATANG DAMAR LAUT AND SSU AIRPORT TO PPU TELUK KUMBAR : MILL AND PAVE WORK
- KAMPUNG MELAYU AND PADANG TEMBAK HOUSING : DAERAH TIMUR LAUT - LIFT SYSTEM
- PEKAN SG DUA TO MAIN PIPE PASAR SG DUA - PIPE INSTALLATION
Need this for every project in your market?
A myBina subscription covers projects across all 13 states and every category: the companies on each project with phone, email and the person in charge where known, plus the stage of works and alerts when a project you follow is updated.
Get Subscription Pricing