Overview: JALAN SIMPANG PULAI/LOJING/GUA MUSANG (FT185, SECTION 65.1) - SLOPE REHABILITATION WORKS is a government Slope construction project in Kelantan. JALAN SIMPANG PULAI/LOJING/GUA MUSANG is currently recorded at Construction - Site Works, with external and finishing works in progress. The main contractor has been awarded. Construction started Jul 2012, with target completion Sep 2013. The project value is recorded in the Between 10 and 50 million range. myBina has identified 4 companies across 3 roles on JALAN SIMPANG PULAI/LOJING/GUA MUSANG: 1 developer, 2 engineers and 1 contractor. This record was last verified on 4 April 2013 (Issue 201304.3).
| Project ID | : | 37011 |
| Issue Number | : | 201304.3 |
| Project Status | : | Construction - Site Works |
| Job Award Status | : | Main contractor awarded |
| State | : | Kelantan |
| Category | : | Slope |
| Full Address | : | |
| Construction Start | : | Jul 2012 |
| Target Completion | : | Sep 2013 |
| Project Ownership | : | Government |
| Value Range | : | Between 10 and 50 million |
| Project Value | : | |
| Contractor Spec | : | |
| Tender Deadline | : |
Full project details are on record for JALAN SIMPANG PULAI/LOJING/GUA MUSANG (FT185, SECTION 65.1) - SLOPE REHABILITATION WORKS, covering the scope of works, site arrangement and contract structure. Available to myBina subscribers.
Recorded specifications for this project cover structural, M&E and finishes requirements, alongside contractor grade and tender details. Available to myBina subscribers.
myBina has identified 4 companies across 3 roles on JALAN SIMPANG PULAI/LOJING/GUA MUSANG (FT185, SECTION 65.1) - SLOPE REHABILITATION WORKS: 1 developer, 2 engineers and 1 contractor.
Contact us to reveal company names, phone numbers, emails and full contact details.
Other Slope construction projects recorded by myBina in Kelantan:
- ROUTE FT185 SECTION 5.3 JALAN GUA MUSANG-KUALA BERIS/LOJING - SLOPE FAILURE WORKS
- EAST COAST RAIL LINK (ECRL) - GOMBAK TO TUMPAT (PHASE 1)
- TEACHERS QUARTERS TAMAN SERI WANGI GUA MUSANG - RETAINING WALL WORKS
- FELDA KEMAHANG 2 & 3 - ROAD RESURFACING WORKS
- CENTRAL SPINE ROAD - PACKAGE 1B : PASIR HOR TO KADOK
Need access to all 10,000+ projects?
A myBina membership gives you unlimited access across all states, categories and project statuses — with alerts, CRM tools and export features.
Contact Us