Overview: BANDAR JASIN BESTARI (PHASE 3) - SUBSTATION (PPU) is a Substation construction project in Melaka. BANDAR JASIN BESTARI is currently recorded at Construction - Structural, with superstructure works in progress. The main contractor has been awarded. Construction started Apr 2013, with target completion Mar 2013. The project value is recorded in the Between 1 and 10 million range. myBina has identified 3 companies across 3 roles on BANDAR JASIN BESTARI: 1 developer, 1 mech. / electrical engineer and 1 contractor. This record was last verified on 25 July 2013 (Issue 201307.3).
| Project ID | : | 38631 |
| Issue Number | : | 201307.3 |
| Project Status | : | Construction - Structural |
| Job Award Status | : | Main contractor awarded |
| State | : | Melaka |
| Category | : | Substation |
| Full Address | : | |
| Construction Start | : | Apr 2013 |
| Target Completion | : | Mar 2013 |
| Project Ownership | : | Private |
| Value Range | : | Between 1 and 10 million |
| Project Value | : | |
| Contractor Spec | : | |
| Tender Deadline | : |
Full project details are on record for BANDAR JASIN BESTARI (PHASE 3) - SUBSTATION (PPU), covering the scope of works, site arrangement and contract structure. Available to myBina subscribers.
Recorded specifications for this project cover structural, M&E and finishes requirements, alongside contractor grade and tender details. Available to myBina subscribers.
myBina has identified 3 companies across 3 roles on BANDAR JASIN BESTARI (PHASE 3) - SUBSTATION (PPU): 1 developer, 1 mech. / electrical engineer and 1 contractor.
Contact us to reveal company names, phone numbers, emails and full contact details.
Other Substation construction projects recorded by myBina in Melaka:
- KOMPLEKS KEMENTERIAN DALAM NEGERI CAWANGAN MELAKA - MECHANICAL & ELECTRICAL WORKS
- (PPU) 33/11KV MUKIM TANGGA BATU - MAIN SUBSTATION BUILDING
- (PPU) 33/11KV UNIVERSITI TEKNOLOGI MARA (UITM) CAMPUS JASIN - MAIN SUBSTATION BUILDING
- (PPU) 33/11KV TAMAN BELIMBING SETIA - MAIN SUBSTATION BUILDING
- PMU MALIM JAYA 132/11kV & PMU UJONG PASIR 132/33kV - ARC PROTECTION SCHEME
Need access to all 10,000+ projects?
A myBina membership gives you unlimited access across all states, categories and project statuses — with alerts, CRM tools and export features.
Contact Us