Overview: DAERAH MANJUNG : PHASE III - PIPING WORKS (CONTRACT 5) is a government Piping Works construction project in Perak. DAERAH MANJUNG : PHASE III is currently recorded at Construction - Site Works, with external and finishing works in progress. The main contractor has been awarded. Construction started Oct 2014, with target completion May 2015. The project value is recorded in the Between 1 and 10 million range. myBina has identified 3 companies across 3 roles on DAERAH MANJUNG : PHASE III: 1 developer, 1 consultant and 1 contractor. This record was last verified on 27 January 2015 (Issue 201501.3).
| Project ID | : | 45655 |
| Issue Number | : | 201501.3 |
| Project Status | : | Construction - Site Works |
| Job Award Status | : | Main contractor awarded |
| State | : | Perak |
| Category | : | Piping Works |
| Full Address | : | |
| Construction Start | : | Oct 2014 |
| Target Completion | : | May 2015 |
| Project Ownership | : | Government |
| Value Range | : | Between 1 and 10 million |
| Project Value | : | |
| Contractor Spec | : | |
| Tender Deadline | : |
Full project details are on record for DAERAH MANJUNG : PHASE III - PIPING WORKS (CONTRACT 5), covering the scope of works, site arrangement and contract structure. Available to myBina subscribers.
Recorded specifications for this project cover structural, M&E and finishes requirements, alongside contractor grade and tender details. Available to myBina subscribers.
myBina has identified 3 companies across 3 roles on DAERAH MANJUNG : PHASE III - PIPING WORKS (CONTRACT 5): 1 developer, 1 consultant and 1 contractor.
Contact us to reveal company names, phone numbers, emails and full contact details.
Other Piping Works construction projects recorded by myBina in Perak:
- PEJABAT PENGURUSAN NEGERI PERAK (KAMPUNG GAJAH) - CIVIL WORKS
- PEJABAT PENGURUSAN NEGERI PERAK (PMU CHENDEROH) - CIVIL WORKS
- PMU MERU RAYA - 132/33kV CABLE EXTENSION (2X90MVA)
- PMU TASEK CEMENT TO SSU UAC - 33KV ALUMINIUM XLPE SINGLE CORE UNDERGROUND CABLES
- LOJI AIR GUNUNG SEMANGGOL (PHASE 3) - RAW WATER PUMP (CONTRACT 6A)
Need access to all 10,000+ projects?
A myBina membership gives you unlimited access across all states, categories and project statuses — with alerts, CRM tools and export features.
Contact Us