Overview: PMU BAYAN LEPAS TO SUNGAI ARA, PENANG - DOUBLE CIRCUIT 132KV UNDERGROUND CABLES is a government Cable Works construction project in Pulau Pinang. The scope is recorded as New Construction. PMU BAYAN LEPAS TO SUNGAI ARA, PENANG is currently recorded at Construction - Site Works, with external and finishing works in progress. The main contractor has been awarded. Construction started Dec 2022. The project value is recorded in the Between 50 and 100 million range. myBina has identified 4 companies across 4 roles on PMU BAYAN LEPAS TO SUNGAI ARA, PENANG: 1 developer, 1 consultant, 1 contractor and 1 sub contractor. This record was last verified on 17 January 2023 (Issue 202304.1).
| Project ID | : | 88622 |
| Issue Number | : | 202304.1 |
| Project Status | : | Construction - Site Works |
| Job Award Status | : | Main contractor awarded |
| State | : | Pulau Pinang |
| Category | : | Cable Works |
| Full Address | : | |
| Construction Start | : | Dec 2022 |
| Target Completion | : | — |
| Project Ownership | : | Government |
| Project Works | : | New Construction |
| Value Range | : | Between 50 and 100 million |
| Project Value | : | |
| Contractor Spec | : | |
| Tender Deadline | : |
Full project details are on record for PMU BAYAN LEPAS TO SUNGAI ARA, PENANG - DOUBLE CIRCUIT 132KV UNDERGROUND CABLES, covering the scope of works, site arrangement and contract structure. Available to myBina subscribers.
Recorded specifications for this project cover structural, M&E and finishes requirements, alongside contractor grade and tender details. Available to myBina subscribers.
myBina has identified 4 companies across 4 roles on PMU BAYAN LEPAS TO SUNGAI ARA, PENANG - DOUBLE CIRCUIT 132KV UNDERGROUND CABLES: 1 developer, 1 consultant, 1 contractor and 1 sub contractor.
Company names, phone numbers, emails and full contact details are included in a myBina subscription.
Other Cable Works construction projects recorded by myBina in Pulau Pinang:
- PERBADANAN BEKALAN AIR PULAU PINANG (SEBERANG PERAI) - AIR CONDITIONING SYSTEM (2 YEARS)
- KOMPLEKS MAHKAMAH PULAU PINANG - MECHANICAL AND ELECTRICAL WORKS
- KAMPUNG SELAMAT, TASEK GELUGOR - WATER TREATMENT SYSTEM
- MAJLIS BANDARAYA PULAU PINANG (PHASE 2) - LIGHTING REPLACEMENT WORKS
- PANGSAPURI PELANGI, GAT LEBUH MACALLUM - WATER TANK AND WATERPROOFING
Need this for every project in your market?
A myBina subscription covers projects across all 13 states and every category: the companies on each project with phone, email and the person in charge where known, plus the stage of works and alerts when a project you follow is updated.
Get Subscription Pricing