Overview: PICCOLO 2 @ BANDAR PUTRA KULAI - LINKHOUSES is a Linkhouses construction project in Johor. The scope is recorded as New Construction. PICCOLO 2 @ BANDAR PUTRA KULAI is currently recorded at Construction - Piling & Foundation Works, with substructure works underway on site. The main contractor has been awarded. Construction started Apr 2024, with target completion Sep 2026. The project value is recorded in the Between 50 and 100 million range. myBina has identified 9 companies across 9 roles on PICCOLO 2 @ BANDAR PUTRA KULAI: 1 developer, 1 civil / structural engineer, 1 mech. / electrical engineer, 1 architect / planner and 5 other roles. This record was last verified on 24 July 2023 (Issue 202308.3).
| Project ID | : | 91017 |
| Issue Number | : | 202308.3 |
| Project Status | : | Construction - Piling & Foundation Works |
| Job Award Status | : | Main contractor awarded |
| State | : | Johor |
| Category | : | Linkhouses |
| Full Address | : | |
| Construction Start | : | Apr 2024 |
| Target Completion | : | Sep 2026 |
| Project Ownership | : | Private |
| Project Works | : | New Construction |
| Value Range | : | Between 50 and 100 million |
| Project Value | : | |
| Contractor Spec | : | |
| Tender Deadline | : |
Full project details are on record for PICCOLO 2 @ BANDAR PUTRA KULAI - LINKHOUSES, covering the scope of works, site arrangement and contract structure. Available to myBina subscribers.
Recorded specifications for this project cover structural, M&E and finishes requirements, alongside contractor grade and tender details. Available to myBina subscribers.
myBina has identified 9 companies across 9 roles on PICCOLO 2 @ BANDAR PUTRA KULAI - LINKHOUSES: 1 developer, 1 civil / structural engineer, 1 mech. / electrical engineer, 1 architect / planner and 5 other roles.
Contact us to reveal company names, phone numbers, emails and full contact details.
Other Linkhouses construction projects recorded by myBina in Johor:
- BENUA KURNIA SDN BHD - CLUSTER HOUSES @ JOHOR BAHRU (PHASE 1B & 2B)
- ARECA TERRACE @ BANDAR UDA UTAMA - LINKHOUSES (PHASE 4A)
- M TIARA @ SKUDAI, JOHOR BAHRU - LINKHOUSES (PHASE 1A)
- ARECA TERRACE @ BANDAR UDA UTAMA - LINKHOUSES (PHASE 4B)
- SONATIA PARK HOMES @ BANDAR PUTRA, KULAI - LINKHOUSES (ZONE 4E & 5E)
Need access to all 10,000+ projects?
A myBina membership gives you unlimited access across all states, categories and project statuses — with alerts, CRM tools and export features.
Contact Us