Overview: PMU GELANG PATAH TO AIRTRUNK DATA CENTRE @ JOHOR - UNDERGROUND CABLES is a government Substation construction project in Johor. The scope is recorded as New Construction. PMU GELANG PATAH TO AIRTRUNK DATA CENTRE is currently recorded at Construction - Site Works, with external and finishing works in progress. The main contractor has been awarded. Construction started Jul 2023, with target completion Nov 2023. The project value is recorded in the Between 10 and 50 million range. myBina has identified 3 companies across 3 roles on PMU GELANG PATAH TO AIRTRUNK DATA CENTRE: 1 developer, 1 contractor and 1 sub contractor. This record was last verified on 6 July 2023 (Issue 202307.3).
| Project ID | : | 91086 |
| Issue Number | : | 202307.3 |
| Project Status | : | Construction - Site Works |
| Job Award Status | : | Main contractor awarded |
| State | : | Johor |
| Category | : | Substation |
| Full Address | : | |
| Construction Start | : | Jul 2023 |
| Target Completion | : | Nov 2023 |
| Project Ownership | : | Government |
| Project Works | : | New Construction |
| Value Range | : | Between 10 and 50 million |
| Project Value | : | |
| Contractor Spec | : | |
| Tender Deadline | : |
Full project details are on record for PMU GELANG PATAH TO AIRTRUNK DATA CENTRE @ JOHOR - UNDERGROUND CABLES, covering the scope of works, site arrangement and contract structure. Available to myBina subscribers.
Recorded specifications for this project cover structural, M&E and finishes requirements, alongside contractor grade and tender details. Available to myBina subscribers.
myBina has identified 3 companies across 3 roles on PMU GELANG PATAH TO AIRTRUNK DATA CENTRE @ JOHOR - UNDERGROUND CABLES: 1 developer, 1 contractor and 1 sub contractor.
Contact us to reveal company names, phone numbers, emails and full contact details.
Other Substation construction projects recorded by myBina in Johor:
- KAMPUS UNIVERSITI TEKNOLOGI MALAYSIA, JOHOR BAHRU - ELECTRICAL WORKS
- HOSPITAL SULTANAH FATIMAH, MUAR - SEWAGE TREATMENT PLANT SYSTEM
- KECK SENG (MALAYSIA) SDN BHD - ELECTRICAL SUBSTATION
- HOSPITAL SULTANAH AMINAH, JOHOR BAHRU : MECHANICAL & ELECTRICAL WORKS
- KOMPLEKS MAHKAMAH MUAR @ JOHOR - MECHANICAL AND ELECTRICAL WORKS (2 YEARS)
Need access to all 10,000+ projects?
A myBina membership gives you unlimited access across all states, categories and project statuses — with alerts, CRM tools and export features.
Contact Us