Overview: AIMS DATA CENTRE SDN BHD - DATA CENTRE @ CYBERJAYA (PHASE 3) is a Data Centre construction project in Selangor. The scope is recorded as New Construction. AIMS DATA CENTRE SDN BHD is currently recorded at Construction - Structural, with superstructure works in progress. The main contractor has been awarded. Construction started Mar 2024. The project value is recorded in the Between 50 and 100 million range. myBina has identified 9 companies across 8 roles on AIMS DATA CENTRE SDN BHD: 1 developer, 1 civil / structural engineer, 2 mech. / electrical engineers, 1 quantity surveyor and 4 other roles. This record was last verified on 25 October 2024 (Issue 202410.3).
| Project ID | : | 95282 |
| Issue Number | : | 202410.3 |
| Project Status | : | Construction - Structural |
| Job Award Status | : | Main contractor awarded |
| State | : | Selangor |
| Category | : | Data Centre |
| Full Address | : | |
| Construction Start | : | Mar 2024 |
| Target Completion | : | — |
| Project Ownership | : | Private |
| Project Works | : | New Construction |
| Value Range | : | Between 50 and 100 million |
| Project Value | : | |
| Contractor Spec | : | |
| Tender Deadline | : |
Full project details are on record for AIMS DATA CENTRE SDN BHD - DATA CENTRE @ CYBERJAYA (PHASE 3), covering the scope of works, site arrangement and contract structure. Available to myBina subscribers.
Recorded specifications for this project cover structural, M&E and finishes requirements, alongside contractor grade and tender details. Available to myBina subscribers.
myBina has identified 9 companies across 8 roles on AIMS DATA CENTRE SDN BHD - DATA CENTRE @ CYBERJAYA (PHASE 3): 1 developer, 1 civil / structural engineer, 2 mech. / electrical engineers, 1 quantity surveyor and 4 other roles.
Company names, phone numbers, emails and full contact details are included in a myBina subscription.
Other Data Centre construction projects recorded by myBina in Selangor:
- GOOGLE DATA CENTRE : ELMINA BUSINESS PARK (EBP1-1A) (MARMORT DC)
- ALAM PERDANA CENTRAL HUB @ PUNCAK ALAM - LOW COST TERRACE INDUSTRIAL & LINK FACTORY (PHASE 1)
- ALAM PERDANA CENTRAL HUB @ PUNCAK ALAM - SEMI DETACHED FACTORY (PHASE 2)
- CHANNEL SYSTEMS ASIA SDN BHD - FACTORY AND OFFICES @ BANDAR BUKIT RAJA
- BIG PHARMACY HEALTHCARE SDN BHD - WAREHOUSE AND OFFICES @ TAMAN PERINDUSTRIAN BUKIT RAJA
Need this for every project in your market?
A myBina subscription covers projects across all 13 states and every category: the companies on each project with phone, email and the person in charge where known, plus the stage of works and alerts when a project you follow is updated.
Get Subscription Pricing